PUBLIC NOTICE. The Georgia Environmental Protection Division is providing public notice of the following proposed orders:



Under authority of the Water Quality Control Act (including Surface Water Allocation) :

Facility: D.L. Lee & Sons, Inc.
Location: Bacon County
Order Number: EPD-WQ-8217
Cause of Order: Violations of the facility's effluent limits occuring in July, August, September and October 2016  
Requirement(s) of Order:     The violations are being corrected through Consent Order EPD-WQ-8162  
Settlement Amount: $4000.00 
Date Notice Posted: March 20, 2017
Comment Period Closes: April 19, 2017
Send Comments To: Dr. Bert Langley-Manager/Mountain District
Environmental Protection Division
Post Office Box 3250
Cartersville, Georgia 30120

Facility: Town of Trion WPCP
Location: Chattooga County
Order Number: EPD-WQ-8245
Cause of Order: Exceeded the permit limitation for Total Ammonia Nitrogen  
Requirement(s) of Order:     Cited violations have been corrected.  
Settlement Amount: $1388.00 
Date Notice Posted: March 20, 2017
Comment Period Closes: April 19, 2017
Send Comments To: Dr. Bert Langley-Manager/Mountain District
Environmental Protection Division
Post Office Box 3250
Cartersville, Georgia 30120

Facility: Premier Yarn Dyers, Inc.
Location: Bartow County
Order Number: EPD-WQ-8244
Cause of Order: Failure to comply with existing order  
Requirement(s) of Order:     Submit an Industrial Pretreatment permit application and comply with the interim effluent limits until the new permit is issued.  
Settlement Amount: $15500.00 
Date Notice Posted: March 06, 2017
Comment Period Closes: April 05, 2017
Send Comments To: Dr. Bert Langley-Manager/Mountain District
Environmental Protection Division
Post Office Box 3250
Cartersville, Georgia 30120

Facility: City of Arlington Wood Valley Road WPCP
Location: Early County
Order Number: EPD-WQ-6114-1
Cause of Order: WPCP Improvements to collection system and plant  
Requirement(s) of Order:     Installation of 14,000 LF of CIPP piping to sewer system, modifications to 3 lift stations, dredging sludges within treatment pond and minor modifications to existing treatment plant.  
Settlement Amount:  
Date Notice Posted: February 27, 2017
Comment Period Closes: March 29, 2017
Send Comments To: Dr. Bert Langley-Manager/Mountain District
Environmental Protection Division
Post Office Box 3250
Cartersville, Georgia 30120


Copies of proposed orders are provided at no charge. To order copies, call 1-888-373-5947 (404/657-5947 inside Atlanta dialing area).